Bac Giang: General inspection of the constructed biogas plants under the LCASP project in the province

: Monday - 08/05/2017 11:35  |  Viewed: 1372
Throughout the inspection of the existing biogas plants, the overall quality of construction work of the project's construction workers, the consultants of the district technician, the awareness of the people About the project and the efficiency of the biogas works to households; This will be the practical basis for the next deployment phase.
In March 2017, Bac Giang PPMU carried out a random inspection of the biogas plants under construction in the province of Bac Giang to assess the quality of the works that have been put into operation and are mechanical Facility for the construction of livestock waste disposal activities in the coming time.
Bac Giang province has built and put into operation 7,000 small size biogas plants (100% of the plan allocated from the central government). Of which, 2,500 works completed in 2016; 4500 works have been built in 2015 and 2014.
The summit will focus on all of the biogas plants under the project for the three years 2014, 2015 and 2016. Therefore, we will have a more general look at the quality of the works over the years.
Through inspections show that the quality of construction works in 2016 works well, the items have not damaged anything until the time of inspection. Works constructed during the first two years of the project (2014 and 2015) are generally well maintained, with some minor damage (mainly gas pipelines, gas station valves and stoves. ). However, these factors can be overcome. Particularly, during the inspection, the mason team is responsible for checking all construction items and guiding and supporting the people to overcome the above mentioned damage phenomena.
Through the general inspection of the existing biogas plants, the overall quality of the construction work of the construction workers under the project, the consultant work of the district technician, the perception of the people People on the project and efficiency of the biogas works to households; This will be the practical basis for the next deployment phase.